RESIDENT NOTIFICATIONS
Greenwood Blasting Update
Stay informed on active schedules and community notifications for the blasting and rock removal phase of the Greenwood project.
Latest Operational Schedule
Week of Oct 26 - 31
Install site security, fencing and signage continues
Blasting/Excavation in zones 2 & 3 continues
Blasting/Excavation in zone 4
Next week (Nov 2 - 7):
Blasting/Excavation in zone 5 - lift 1, and 6 - lift 1
View our Blasting Plan Summary showing the 8 operational blasting zones for the Greenwood project and a brief explanation of how blasting will progress across the site. Refer to this document to identify active work areas referenced in our weekly schedule updates.
Click here to view or download the Blasting Plan Summary (PDF) ↗
Standard Safety Protocols & Horn Blasts
Note: To keep traffic delays to an absolute minimum, the blaster in charge and the fire detail mutually agreed to compress the traditional warning intervals down to the time needed to finish the visual and drone inspections.
5 Minutes to Blast
3 audible signal pulses
1 Minute to Blast
2 audible signal pulses
All Clear
1 long audible signal pulse
Subscribe to Email Notifications
Option 1: Complete Subscription Form
Complete the form to receive weekly Friday schedule summaries and immediate alerts for late-breaking operational changes.
Option 2: Direct Email Request
Prefer direct correspondence?
Email greenwood@szecon.com with the subject line "Subscribe to Greenwood Updates" including your name and address.